What are the procedure of construction of a well foundation?

Construction of well foundation 

Work is done during non-monsoon months of the year 

Islolate the area by making bund around it so that river water flows 
beyond e isthlnda. Sheet piling is also resorted where bed is 
deep 

Low height Sand island is created as platform over which cutting edge of steel 
for well curb is placed and well curb is cast with some steining height 
(may be 1.5 to 3.0m) 

Kentelage (load ) is applied through platform at top of steining, cast so far, 
to sink the steining and simultaneously dredging of material from inside is resorted. 

Keep Casting steining and applying kentelage to sink it.A minium 48 Hrs curing time 
is must for steining after its casting for it to be ready for sinking. 


Initially the sinking will be faster and inside dredging is easy due to soft top strata 
Once steining get sunk deeper, there is enough friction from sides.Dredging from inside will 
need effort for sinking it ( before loading it) thru trained divers(with oxygen mask) who go 
below and dredge at bottom of steining since river water seeps into well 

The process goes on for one or more seasons depending upon depth of sinking. 
The sinking process is slow and time taking.Half constructed wells 
have to see the flash floods of river when islands and bunds wash away 
during monsoon. 

Once final level is achieved, well is plugged at bottom with rich concrete as per 
drg and specifications.This is bottom plug. 

Well upto nearly mid-height is filled with sand(or excavated material free 
from organic matter) and again plugged with rich concrete 
acting as intermediate plug. 

From intermediate plug upto well cap soffit level , the well is filled with 
sand/exc material and well cap is cast.