PROTECTION OF BUILDINGS AGAINST DAMPNESS

PROTECTION OF BUILDINGS AGAINST DAMPNESS

One of the requirements of the building is that it should be dry. Dampness in a building may occur due to bad design, faultyconstruction and use of poor quality of materials. Dampness not only affects the life of the building but also creates unhygienic conditions of the important items of work in the construction of a building. The treatment given to prevent leakage of water from roof is generally termed as water proofing whereas the treatment given to keep the walls, floors and basement dry is termed as damp proofing.

DEFECTS OF DAMPNESS IN BUILDINGS:

The various defects caused by dampness to building may be summarized as under:
  1. It causes efflorescence which may ultimately result in disintegration of bricks, stones, tiles etc.
  2. It may result in softening and crumbling of plaster.
  3. It may cause bleaching and flaking of paint with the formation of coloured patches.
  4. It may result in the warping, buckling and rotting of timber.
  5. It may lead to the corrosion of metals.

Excavations

The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then, OSHA has amended the standard several times to increase worker protection and to reduce the frequency and severity of excavation accidents and injuries. Despite these efforts, excavation-related accidents resulting in injuries and fatalities continue to occur.

To better assist excavation firms and contractors, OSHA completely updated the existing standard to simplify many of the existing provisions, add and clarify definitions, eliminate duplicate provisions and ambiguous language, and give employers added flexibility in providing protection for employees. The standard was effective as of March 5, 1990.

SCOPE AND APPLICATION
OSHA's revised rule applies to all open excavations made in the earth's surface, which includes trenches.

According to the OSHA construction safety and health standards, a trench is referred to as a narrow excavation made below the surface of the ground in which the depth is greater than the width-the width not exceeding 15 feet. An excavation is any man-made cut, cavity, trench, or depression in the earth's surface formed by earth removal. This can include excavations for anything from cellars to highways.

TYPES OF DEEP FOUNDATION

Deep foundations are required to carry loads from a structure through weak compressible soils or fills on to stronger and less compressible soils or rocks at depth, or for functional reasons. These foundations are those founding too deeply below the finished ground surface for their base bearing capacity to be affected by surface conditions, this is usually at depths >3 m below finished ground level. Deep foundations can be used to transfer the loading to a deeper, more competent strata at depth if unsuitable soils are present near the surface.
The types of deep foundations in general use are as follows:
1) Basements
2) Buoyancy rafts (hollow box foundations)
3) Caissons
4) Cylinders
5) Shaft foundations
6) Piles

NUMBER AND SPACING OF PILES IN A GROUP.

Very rarely are structures founded on single piles. Normally, there will be a minimum of three piles
under a column or a foundation element because of alignment problems and inadvertent
eccentricities. The spacing of piles in a group depends upon many factors such as

1. overlapping of stresses of adjacent piles,
2. cost of foundation,
3. efficiency of the pile group.

The pressure isobars of a single pile with load Q acting on the top are shown in Fig. 15.24(a).

When piles are placed in a group, there is a possibility the pressure isobars of adjacent piles will overlap each other as shown in Fig. 15.24(b). The soil is highly stressed in the zones of overlapping of pressures. With sufficient overlap, either the soil will fail or the pile group will settle excessively since the combined pressure bulb extends to a considerable depth below the base of the piles. It is possible to avoid overlap by installing the piles further apart as shown in Fig. 15.24(c). Large spacings are not recommended sometimes, since this would result in a larger pile cap which would increase the cost of the foundation.

Respiratory and Allergic Health Effects of Dampness,

Abstract

Objectives

Many studies have shown consistent associations between evident indoor dampness or mold and respiratory or allergic health effects, but causal links remain unclear. Findings on measured microbiologic factors have received little review. We conducted an updated, comprehensive review on these topics.

Data sources

We reviewed eligible peer-reviewed epidemiologic studies or quantitative meta-analyses, up to late 2009, on dampness, mold, or other microbiologic agents and respiratory or allergic effects.

Data extraction

We evaluated evidence for causation or association between qualitative/subjective assessments of dampness or mold (considered together) and specific health outcomes. We separately considered evidence for associations between specific quantitative measurements of microbiologic factors and each health outcome.

MATERIALS USED FOR DAMP PROOFING

Material used for damp proofing
1. Property of the material

An effective damp proofing material should have the following properties
1.      It should be impervious.
2.      It should be strong and durable and should be capable of withstanding both dead as well as live loads without damage.
3.      It should be dimensionally stable
4.      It should be free from deliquescent salts like sulphates chlorides and nitrates
5.      The material should be reasonably cheap.
6.      The material should be such that it is possible to carry out leak proof joining work.



  2. Classification of material
                      The materials commonly used to check dampness can be divided into the following four categories
a)      Flexible material
Material like bitumen felts (which may be Hessian based or fibre/glass fibre based), plastic sheeting (polythene sheet) etc
b)     Semi rigid materials
Materials like mastic asphalts or combination of materials or layers.
c)      Rigid materials
Materials like first class bricks, stones, slates, cement concrete etc
d)     Grout materials 
Grout consists of cement slurry and acrylic based chemical or polymers.

NATURE AND CAUSES OF BUILDING DAMPNESS

While water molecules are present in the air and adsorbed on materials within all buildings, when the materials become sufficiently damp to cause material damage or visible mold growth we often say that the building has excess dampness or a dampness problem or we characterize the building as a damp building. The dampness and mold growth may occur on visible interior surfaces in the building, including within basements or crawl spaces, or be hidden inside walls and air conditioning systems.
Buildings can become damp through numerous mechanisms including the following [1-4]:
Several houses completely surrounded by flood waters, a satelite view of a hurricane, a house covered in snow.
  • Rain or snow may enter a building through leaks in roofing systems and building envelopes during normal weather or severe storms (e.g., hurricanes). The heating of wet building envelope materials by the sun can also drive moisture through these materials and into adjacent building materials and spaces.

Brick Floors:

The Wood-Pile

Out walking in the frozen swamp one gray day,
I paused and said, 'I will turn back from here.
No, I will go on farther—and we shall see.'
The hard snow held me, save where now and then
One foot went through. The view was all in lines
Straight up and down of tall slim trees
Too much alike to mark or name a place by
So as to say for certain I was here
Or somewhere else: I was just far from home.
A small bird flew before me. He was careful
To put a tree between us when he lighted,
And say no word to tell me who he was
Who was so foolish as to think what he thought.
He thought that I was after him for a feather—
The white one in his tail; like one who takes
Everything said as personal to himself.

CAISSON (PIER) FOUNDATION

Caisson Foundation
  • The foundation system of and the soils beneath the building prevent the complex from moving vertically.
  •  When a load is placed on soil, most soils settle. This creates a problem when the building settles but the utilities do not. Even more critical than settlement is differential settlement.
  •  This occurs when parts of your building settle at different rates, resulting in cracks, some of which may affect the structural integrity of the building. Conversely, in some rare instances soils may swell, pushing your building upwards and resulting in similar problems.
  • Therefore, the foundation system must work in tandem with the soils to support the building.
WHAT IS CAISSONS?
  • It’s a prefabricated hollow box or cylinder
  • It is sunk into the ground to some desired depth and then filled with concrete thus forming a foundation.
  • Most often used in the construction of bridge piers & other structures that require foundation beneath rivers & other bodies of water
  • This is because caissons can be floated to the job site and sunk into place
  • Basically it is similar in form to pile  foundation but installed using different way
  • used when soil of adequate bearing strength is found below surface layers of weak materials such as fill or peat

PREPARATION OF APPROXIMATE CONSTRUCTION ESTIMATE

Preliminary or approximate estimate is required for studies of various aspects of work of project and for its administrative approval. It can decide, in case of commercial projects, whether the net income earned justifies the amount invested or not. The approximate estimate is prepared from the practical knowledge and cost of similar works. The estimate is accompanied by a report duly explaining necessity and utility of the project and with a site or layout plan. A percentage 5 to 10% is allowed for contingencies.
construction-estimation
The following are the methods used for preparation of approximate estimates:
a) Plinth area method
b) Cubical contents methods
c) Unit base method.

A) PLINTH AREA METHOD:

The cost of construction is determined by multiplying plinth area with plinth area rate. The area is obtained by multiplying length and breadth (outer dimensions of building). In fixing the plinth area rate, careful observation and necessary enquiries are made in respect of quality and quantity aspect of materials and labour, type of foundation, height of building, roof, wood work, fixtures, number of storeys etc.

Groundwater Control by Exclusion and Pumping

In dewatering design there is often a presumption that groundwater pumping will be the main means of keeping the excavation dry. In fact, while groundwater control by pumping can be very effective, it is also worth being aware that another approach can be taken – that of groundwater control by exclusion.
It is important to select the correct approach to groundwater control on each project. This blog describes groundwater control by pumping compared with groundwater control by exclusion. It is also important to remember that each project and set of ground conditions are unique and must be assessed individually, and that a groundwater control approach that may work at one site may not work at another.A useful starting point in understanding groundwater control methods is to think about grouping all the techniques into one of two main types: groundwater exclusion or groundwater pumping.
GROUNDWATER CONTROL BY EXCLUSION
This approach is based on installing an impermeable physical cut-off wall around the entire site to exclude groundwater from the excavation. 
This method can, in theory, avoid groundwater pumping, apart from pumping out the water trapped in the area enclosed by the cut-off wall. In reality things can be a bit more complex. Firstly, no cut-off wall is truly impermeable, so there may be small water leaks at joints even in cut-off walls constructed to high standards. Secondly, if a low permeability stratum is not present at a relatively shallow depth below the base of the excavation (for the wall to ‘toe into’) then a cut-off wall cannot completely exclude groundwater from the excavation.

Caissons-Types of caissons

A caisson is a water-tight box like structure or a chamber, made of wood, steel, or concrete, usually sunk by excavating within it, for the purpose of gaining access to the bed of a stream and placing the foundations at a prescribed depth and which subsequently forms part of the foundation itself. Caissons are adopted when the depth of water is great and the foundations are to be laid under water. Caissons are generally built on the shore and launched in to the river floated to the site and sunk at the proper position.
Types of Caissons:
The shape and size of a caisson depends upon the nature of structure for which it is to be built and the depth up to which it is required to be sunk. Caissons can be broadly classified in the following three different types.
(1) Open caisson(2) Box caisson(3) Pneumatic caisson.

(1) Open Caissons:
Depending upon their shape, open caissons can be further classified as,
(i) Single wall open caisson
(ii) Cylindrical open caisson
(iii) Open caisson with dredging wells.

Waterproofing

Waterproofing is making an object virtually impervious to water.

Contents

  
  • 1 Discussion
  • 2 Construction waterproofing
  • 3 Oil-based waterproofing
  • 4 Waterproofing of objects
  • 5 Waterproofing clothing and tents
  • 6 Standard

    Discussion

    Water-proof or water-resistant describes objects relatively unaffected by water or resisting the ingress of water under specified conditions. Such items may be used in wet environments or under water to specified depths. Waterproofingdescribes making an object waterproof or water-resistant (such as a camera, watch or mobile phone).
    "Water resistant" and "waterproof" often refer to penetration of water in its liquid state and possibly under pressure wheredamp proof refers to the resistance to humidity or dampness. Permeation of water vapor through a material or structure is reported as a water vapor 
    Waterproofing conducted on the exterior of a freeway tunnel

    Construction waterproofing

    Main article: weatherization
    In construction, a building or structure is waterproofed with the use of membranes and coatings to protect contents as well as protecting structural integrity. The waterproofing of the building envelope in construction specifications is listed under '07 - Thermal and Moisture Protection' within MasterFormat 2004, by the Construction Specifications Institute, and includes roofing material as well as waterproofing materials[citation needed]. In building construction, waterproofing is a fundamental aspect of creating a building envelope which is a controlled environment.

Cofferdams | Types of Cofferdams

A cofferdam is a temporary enclosure in a river or lake built around a working area for the purpose of excluding ground water and water above ground level during construction.

Types of coffer Dams 

There are various types of cofferdams. They include:

  • Cantilever Sheet Pile Cofferdam
  • Braced Cofferdam
  • Earth Embankment Cofferdam
  • Rockfill Cofferdam
  • Double Wall Cofferdam
  • Cellular Cofferdam
Cantilever Sheet Piles – Cantilever sheet piles are suitable for small head of water about 6 m. They are susceptible to large leakage and flood damage. They can be constructed of wood, concrete and steel. Wooden sheet pile cofferdam is suitable for small head of water i.e. up to 3 m. Steel coffer dam is suitable up to 6 m head of water. Concrete cofferdam is suitable when headroom is limited. Bored and cast in place sheet piles are to be used to avoid noise and vibration. A typical sketch of cantilever sheet pile is shown in Fig.1 below.
cantilever sheet pile coffer dam
Earth Embankment – Earth embankment is suitable for high head of water and low water velocity. The side slopes of the embankment should be 1:3 to 1:4.

Deep foundation

There are many reasons a geotechnical engineer would recommend a deep foundation over a shallow foundation, but some of the common reasons are very large design loads, a poor soil at shallow depth, or site constraints (like property lines). There are different terms used to describe different types of deep foundations including the pile (which is analogous to a pole), the pier (which is analogous to a column), drilled shafts, and caissons. Piles are generally driven into the ground in situ; other deep foundations are typically put in place using excavation and drilling. The naming conventions may vary between engineering disciplines and firms. Deep foundations can be made out of timber, steel, reinforced concrete and prestressed concrete.

Contents

  • 1 Driven foundations
    • 1.1 Pile foundation systems
    • 1.2 Monopile foundation
  • 2 Drilled piles
    • 2.1 Under reamed piles
    • 2.2 Augercast pile
    • 2.3 Pier and grade beam foundation
    • 2.4 Drilled Pier vs. Drilled Pile
  • 3 Speciality piles
    • 3.1 Micropiles
    • 3.2 Tripod piles
    • 3.3 Sheet piles
    • 3.4 Soldier piles
    • 3.5 Suction Piles
    • 3.6 Adfreeze Piles
    • 3.7 Vibrated stone columns
  • 4 Piled walls
    • 4.1 Secant piled walls
    • 4.2 Slurry walls
  • 5 Deep mixing/mass stabilization techniques
  • 6 Classification of pile with respect to type of material
    • 6.1 Timber
    • 6.2 Steel
    • 6.3 Prestressed concrete piles
    • 6.4 Composite piles

      Driven foundations

      Pipe piles being driven into the ground

What are the procedure of construction of a well foundation?

Construction of well foundation 

Work is done during non-monsoon months of the year 

Islolate the area by making bund around it so that river water flows 
beyond e isthlnda. Sheet piling is also resorted where bed is 
deep 

Low height Sand island is created as platform over which cutting edge of steel 
for well curb is placed and well curb is cast with some steining height 
(may be 1.5 to 3.0m) 

Kentelage (load ) is applied through platform at top of steining, cast so far, 
to sink the steining and simultaneously dredging of material from inside is resorted. 

Keep Casting steining and applying kentelage to sink it.A minium 48 Hrs curing time 
is must for steining after its casting for it to be ready for sinking. 

COMPONENTS OF LAMINATE FLOORING

The components of laminate flooring and the components of engineered flooring are similar in a number of ways. Laminate flooring  and engineered wood flooring are also appear much alike to the untrained eye but are not the same product. In this article we discuss the components of laminate flooring. 
Both laminate and engineered floors are available as floating floors made up of tongue-and-groove planks that snap together. Both floors are made in a variety of widths, and an array of colors and wood-grain patterns. The primary difference between the two is that the wood grain and the top surface. With laminate flooring the grain is printed paper and not hardwood and the usual top layer of laminate is melamine plastic. The resulting laminate flooring products can come in thicknesses varying from approximately 6mm to 12mm, the thicker of the laminate floors product being the more durable.anatomy of laminate flooring

COMPONENTS OF LAMINATE FLOORING THE ANATOMY

MELAMINE WEAR LAYER

The top layer is hard wearing thin film like layer which is specifically designed to resist
many forms of abrasion. It is typically made up of several coats of melamine with aluminum oxide giving it a durable and water resistant surface.

DECORATIVE PAPER PRINT LAYER

The next layer from the top what gives the floor its appearance is a digital print layer. The design can range from that of a wood grain to the appearance of cork, stone, ceramic or whatever design the manufacturer chooses to print.

Common Flooring Types

Resilient Flooring
Man-Made Stone Flooring
Natural Stone Flooring


Resilient Flooring
Vinyl Composition Tile (VCT)
Overview and General Characteristics: Vinyl composition tile is the most popular resilient flooring today for commercial applications. These 12” x 12” tiles come in a variety of colors and grades. They are easy to install and are cost effective. VCT offers good dimensional stability, durability, impact resistance, UV light stability and heat stability.
Composition: Approximately 60 - 70% limestone/clay/talc mixture, 15 - 20% binder (filler), 10% vinyl (resin), 5% fiberglass, 3 - 5% plasticizer and 1 - 5% pigment.
Maintenance Characteristics: VCT holds all types and brands of floor finishbeautifully due to its porous nature.



Vinyl Asbestos Tile (VAT)
Overview and General Characteristics: Common resilient flooring that was produced from the mid-1950’s until the mid-1980’s. Much of it was produced in the 9” x 9” size, though 12” x 12” was also available. This flooring hasn’t been produced for health and safety reasons since mid-1980. VAT was known for its durability, dimensional stability and heat resistance as evidenced by the amount still found in older buildings.
Composition: Approximately 50 - 70% limestone, 5 - 20% asbestos, 15 - 20% binder, 5% plasticizer and 0.5 - 5% pigment.
Maintenance Characteristics: This floor accepts finish nicely. Being old and porous, it usually requires a coat or two of sealer if it is stripped (follow OSHA and EPA guidelines for stripping). On very old floors, use of high alkalinestrippers is not recommended.

Stair Construction

The staircase, when carefully designed and built, adds dignity and charm to a home. The quality of craftsmanship displayed reflects the character of the entire interior of the building. In general, stairwork is considered a special field of carpentry. The main stairway, which may have several artistic features that are difficult to make on the job, is usually made in a mill and assembled at the house. Stairs which are usually built by the carpenter on the job include the porch and other stairs on the outside of buildings, and less important stairs within a building. It is essential that every carpenter have the necessary information regarding the general principles involved in stair building, as well as knowledge of the layout and construction. 

Types of Stairs
The staircase in a building is one means whereby one may travel from the level of one floor to another. The ease with which a stairway can be traveled depends upon the proper proportioning of the riser and tread of each step and the number of steps in one series or flight. The design of the building and the space allowed for stairs will control the type of staircase which may be built. Geometrical Stairs. The most complicated and most expensive stairways are those that are curved, commonly known as the geometrical stairway. The geometrical stairway is a winding stairway, but it is so designed that the tread at the line of travel of all steps is the same width. These staircases may be circular as shown at A, or elliptical as at B, Fig. 73, and often are designed with landings to insure ease in ascending them.
pict0.jpg pict1.jpg pict3.jpg
Safety Precautions in Stairway Building
Statistics compiled by the National Safety Council show that stairways are the cause of the greatest number of accidents in the home, These accidents can be attributed to various factors; some, of course, are beyond the control of those who design and build the stairways. However, there are far too many accidents due directly to faulty construction.