GENERAL PRINCIPLES TO BE OBSERVED WHILE LAYING DPC ARE:

  1. The DPC should cover full thickness of walls excluding rendering.
  2. The mortar bed upon which the DPC is to be laid should be made level, even and free from projections. Uneven base is likely to cause damage to DPC.
  3. When a horizontal DPC is to be continued up a vertical face a cement concrete fillet 75mm in radius should be provided at the junction prior to the treatment.
  4. Each DPC should be placed in correct relation to other DPC so as to ensure complete and continuous barrier to the passage of water from floors, walls or roof.
Figures 1 to 7 explain provision of DPC under different conditions
DAMP PROOF COURSE (DPC)
Figure 1: Air Drain
DAMP PROOF COURSE (DPC)
Figure 2: DPC Treatment for basement on undrained soils.
DAMP PROOF COURSE (DPC)
Figure 3: Plan of building showing DPC
DAMP PROOF COURSE (DPC)
Figure 4: DPC treatment for basement in damp soil
DAMP PROOF COURSE (DPC)
Figure 5: Asphalt tanking for basement
DAMP PROOF COURSE (DPC)
Figure 6: DPC for flooring
DAMP PROOF COURSE (DPC)
Figure 7: DPC for internal wall